O2 Rising

January 31, 2024

Graham is steadily progressing with the construction of the O2 Sussex Residential Tower in Metrotown, Burnaby, BC. The tower will comprise of 285 units, along with an adjacent 4-storey wood-framed building providing 53 rental units, all situated above a 4-level underground parking garage.

O2 Sussex will offer a living experience where health and wellness are integrated into every aspect of the design. Features include steam showers, water purifiers, a walk score of 79, and proximity to Central Park.

Visit the O2 website for complete details.

Project Update:

  • Excavation commenced 8 months ago in May 2023, and to date, we have completed shoring, bulk, and detailed excavation.
  • Concrete forming is currently underway, with preparations for pouring the North side P3 deck by January 26, 2024.
  • Slab on grade for the entire site is scheduled for completion by mid-February 2024.
  • On the South side, progress is being made with footing, column, and wall installations, with waterproofing ahead of wall forming and footing install.
  • Plumbing work is ongoing, focusing on catch basins, sub-drains, perimeter drains, and sump pits.
  • Electrical work is progressing with in-slab rough-ins.
  • Underground Civil works on Sussex Avenue is ongoing, with the removal of existing overhead utility lines expected to be completed by March 2024.
  • Slab on Grade for the North section of the site was completed on January 6, 2024.

O2-Sussex-Condo-Burnaby-BC-Graham-news-2

Other Recent News

Cariboo Memorial Hospital Construction Project Update

Cariboo Memorial Hospital Construction Project Update

The Cariboo Memorial Hospital Redevelopment project, undertaken by Interior Health, aims to modernize and expand an aging hospital in Williams Lake, BC, originally built in the 1960s. With a population of approximately 11,000, Williams Lake is also home to the...

Regina Urgent Care Centre Construction Completed

Regina Urgent Care Centre Construction Completed

The new Regina Urgent Care Centre (UCC) reached a construction completion milestone of 100%. The process of hiring staff is currently in progress, and over the next few weeks, the installation and testing of equipment and furnishings will be carried out, according to...